MVP sprint project template

A four-week product MVP: scope, two build sprints, testing and a launch-ready demo.

A short, time-boxed build for a first product version. Week one fixes scope and the technical plan; two one-week sprints build it; the last week tests, fixes and prepares the demo or launch.

Hourly billing by default, with a budget so you see burn against the estimate. Keep the scope list honest: anything new goes to the backlog for after the MVP.

What's in it

  1. Scope and plan

    Day 1–6
    • User stories and must-haves6h
    • Technical plan and architecture6h
    • Clickable prototype8h
    • Scope sign-offChecklist: Must-haves agreed · Out-of-scope list written down1h
  2. Build sprint 1

    Day 7–13
    • Project setup, CI and environments6h
    • Authentication and accounts10h
    • Core feature, part 120h
    • Sprint 1 demo1h
  3. Build sprint 2

    Day 14–20
    • Core feature, part 220h
    • Admin and settings8h
    • Payments or integrations10h
    • Sprint 2 demo1h
  4. Test and launch

    Day 21–29
    • Testing and bug fixesChecklist: Happy paths · Edge cases and errors · Mobile16h
    • Analytics and monitoring4h
    • Launch or investor demo3h
    • Handover and next steps2h